Most scaffolds go up in half a day to a day. How long they stay up depends on the job: a solar install is usually days, a chimney repair one to two weeks, a re-roof or render two to four weeks, and an extension four to eight weeks. These are typical figures, not guarantees; your quote confirms the real ones.
The install itself typically takes one to three days, so the scaffold is up for days rather than weeks. Solar scaffolding.
Repointing typically takes one to three days once access is in place, and the scaffold is usually up for one to two weeks. Chimney scaffolding.
A typical domestic re-roof takes two to five working days on site; the scaffold is normally up for two to four weeks. Roof replacement scaffolding.
Rendering typically takes four days to three weeks and cement-based render usually needs 7–14 days to dry before painting. Scaffold is normally up two to four weeks. Render scaffolding.
Scaffold is typically up for four to eight weeks, and a loft conversion typically takes six to twelve weeks or more. Extension and loft scaffolding.
Tell us as early as you can. Extra weeks typically cost around £50–£150 each, and we will agree how to extend the hire with you before it runs on. For more on hire, see scaffolding hire in Essex, and for prices see the cost guide.
Most standard house scaffolds are erected in half a day to a full day, depending on size. Larger or more complex runs take longer.
Typically two to four weeks for a standard domestic re-roof, including time either side for weather and snagging.
Tell us as early as you can. Extra weeks typically cost around £50–£150 each, and we will agree how to extend the hire with you before it runs on.
Surveys, RAMS, inspections, loading bays and programme planning for builders, developers and property managers.
Read Guide →What to do first when a roof or building needs urgent access, and what to tell a scaffolder.
Read Guide →Independent, chimney, loading bay, birdcage, tower and temporary roof scaffolds explained, with what each is used for.
Read Guide →